LCTI: The San Joaquin Valley Transit Electrification Project
Advanced Technology Demonstration and Pilot Projects
San Joaquin Valley Air Pollution Control District
November 14, 2016 – Spring 2020
Project Details:
The San Joaquin Valley Transit Electrification Project is accelerating the deployment of commercially available heavy-duty, zero-emission, public transit buses to provide public benefits to disadvantaged communities throughout the San Joaquin Valley. This project will serve as a regional-scale deployment to show that California-made battery electric transit buses better serve communities’ transit needs, substantially reduce greenhouse gas emissions, and eliminate criteria emissions—which provides needed public health co-benefits for disadvantaged communities in one of the state’s most challenging regions for attainment of ever tightening air quality standards.
In addition, the scale of the project will drive down per-vehicle zero-emission bus costs and offer tremendous opportunities for shared infrastructure, mechanics, spare parts, and workforce training. The project will result in a regional-scale heavy-duty zero-emission success story that will provide scalable lessons learned to better inform and educate transit fleet operators to help drive additional deployments of zero-emission heavy-duty technologies throughout California.
Grantee:
San Joaquin Valley Air Pollution Control District
Partners:
Partners: Proterra, City of Visalia Transit District, Fresno County Rural Transit Agency, San Joaquin Regional Transit District and City of Modesto Transit Services.
Grant Amount
CARB Contribution | $13,414,215 |
---|---|
Matching Funds | $8,764,606 |
Project Total | $22,178,821 |
Vehicles/Equipment Funded
- The City of Visalia Transit Division has deployed 3 Proterra extended-range buses and 4 depot-chargers.
- Fresno County Rural Transit Agency (FCRTA) has deployed 5 Proterra extended-range buses and 8 depot-chargers.
- San Joaquin RTD has deployed 2 Proterra fast-charge buses and 2 overhead fast chargers.
- The City of Modesto Transit Services has deployed 5 Proterra extended range buses and 8 depot chargers.
Lessons Learned
- Contracting needs more time allocated in the schedule. It can often be lengthy and sometimes lead to project delays.
- Better and more frequent communication between all project partners can help improve efficiency and effectiveness of the project.
- Infrastructure planning and construction should be started in the beginning. This piece always takes longer than expected.
Status Updates
- All electric buses have been deployed and have been providing data collection to third party data collector.
- All charging infrastructure has been delivered and nearly in-place.
- Data collection with Ricardo has concluded and data from all partners is being analyzed.